Guidelines for Proposed Development Adjacent to Watershed Project Dams

There is a need for statewide uniformity when there are proposed changes that will have an impact to the function and maintenance of a watershed dam or adjacent pertinent areas. The Natural Resources Conservation Service (NRCS) has developed review guidelines for any proposed development adjacent to a watershed project dam.

Definitions of terminology used herein include:

A dam is an artificial barrier, together with any associated spillways and appurtenant works, across a watercourse or natural drainage area, which does or may impound or divert water.

small_Picture 271.jpg

The top of dam is the lowest elevation along the centerline of the dam. This does not include any elevations within the auxiliary spillway.

The auxiliary spillway is the spillway designed to convey excess water through, over, or around a dam.  The auxiliary spillway is usually an excavated channel through one or both of the abutments.

The control section in an open channel spillway is that section where accelerated flow passes through critical depth. 

The impoundment area is the portion of the reservoir allotted to the temporary storage of floodwater.  Its upper limit is the top of dam elevation.

An easement is a legal document granted to the Sponsoring Local Maintenance Organization(s), which covers the impoundment area and the auxiliary spillway(s) return flow to the waterway downstream from the dam. 

All NRCS watershed dams within the State of Georgia have a Sponsoring Local Maintenance Organization(s) (Sponsor) with most being in one of the below categories.

  1. The Local Soil and Water Conservation District (district),
  2. The district and the County or City,
  3. The County or City.  (Some Sponsors own the dam and impoundment area)

The actual easement elevation varies with each watershed structure.  Easements can reference the top of dam elevation, the auxiliary spillway control section elevation, or the auxiliary spillway control section elevation plus flow depth.  Also, some easements contain special provisions.  Easements belong to the Sponsor. 

Assistance is available to the Sponsor from the State Attorney General through the Georgia Soil and Water Conservation Commission (GSWCC) for legal problems related to easements and land rights

The Sponsor is responsible for proper operation and maintenance of the dam and issuing or denying requests for changes within the impoundment area.

The Sponsor should notify the NRCS when proposed changes are planned that will have an impact to the functioning and maintenance of a watershed dam.

Proposed changes of concern include:

  1. Any roads, sewer lines, or other utilities across, on or through the dam, auxiliary spillway or within the impoundment area.
  2. Any plans that include earthfill within the impoundment area.
  3. Any plans which propose structures, buildings, fences, play areas, trails or other items within the impoundment area, auxiliary spillway, or on the dam.
  4. Any plans to utilize the impoundment area as stormwater detention.
small_dam4.jpg

When the above or similar proposed changes are planned, the designer must submit two sets of drawings, specifications and any applicable hydrology and hydraulic reports to the Sponsor for routing to NRCS engineers through the designated District Conservationist.  Any submittals for proposed earthfill or stormwater detention within the impoundment area shall include calculations to verify compensation of effected volumes.  All submittals shall include a designated contact person.

NRCS engineers make reviews as to compliance with NRCS criteria and provide recommendations and comments regarding the proposed changes to the Sponsor.  Changes that include installation of sewer lines, water lines, or any modifications to the dam, principal spillway or auxiliary spillway will require review of the NRCS State Conservation Engineer.  During the review process, NRCS engineers may contact the designated contact person for clarification or to suggest changes that could bring a project into NRCS criteria compliance.

Upon completion of the review the NRCS engineer will provide final recommendations and comments to the NRCS District Conservationist for routing to the Sponsor.  The Sponsor decides whether to permit proposed changes or deny proposed changes if these changes will have adverse impacts on maintenance, liability or proper functioning of a dam.

Development activities that should not be allowed in areas adjacent to the easement, impoundment area, auxiliary spillway or dam include:

  1. Any activity that decreases flood storage volume such as any modification to the principal spillway riser that would increase normal water surface elevation.
  2. Erection of structures, buildings, signs, fences, or landscaping features on the dam or in the auxiliary spillway which would interfere with the proper functioning of the structure or inhibit maintenance activities such as annual mowing of these areas.
  3. Docks, picnic tables or other potential floating items should not be permitted unless anchored in such a way that they cannot float loose with fluctuations in the lake level.

The State of Georgia classifies dams as Category I if a failure of that dam would cause probable loss of life downstream.  The State of Georgia EPD Safe Dams Section must approve plans for proposed changes through or near the dam or auxiliary spillway of Category I dams.

Examples include sewer lines, roads, or structures that require rock blasting near the dam or other significant topographic changes.

General NRCS recommendations to Sponsors and Designers:

small_SR29_pre-dam_ maintenance-2013.jpg
  1. Enforce the State of Georgia Erosion and Sediment Control Law within the drainage area of the watershed dam to keep sedimentation accumulation in the impoundment area to a minimum.
  2. Enforce Storm Water Management Requirements on new development sites within the drainage area of a watershed dam and prohibit increases in peak runoff into the impoundment area.
  3. Proposed development adjacent to the lake should construct detention pond(s) according to local stormwater ordinances with the top of dam elevation above the NRCS structure’s 100 year-24 hour water surface elevation.  In cases where a detention pond is not feasible, a volume equal to the increased runoff amount for the 100 year-24 hour storm event may be excavated between the auxiliary spillway crest elevation and normal pool.  NRCS will depend upon the County or Local City Government(s) to insure that all disturbed areas are properly re-vegetated in a timely manner.
  4. Forward all plans for areas being developed adjacent to the impoundment area to NRCS for comment with enforcement responsibilities remaining with the Local Government
  5. Not allow construction of houses in the dam breach zone.  Such construction would cause the dam to become Category I leaving the Local Government and or others responsible for expensive modifications.
  6. Not allow any structures, such and houses or commercial buildings, to be constructed in the impoundment area, unless the lowest finished floor elevation of the structure is above the design top of dam elevation.